所有鋁窗必須100% 全數進行抆泥試水
Water-Tightness Test to Window Grouting
測試方法和程序
Testing
Method and Requirements:
Test to Window Grouting
Time :
|
Conduct
test as early as practicable before the commencement of external wall rendering. (Curtain wall system, internal windows and
aluminium louvres shall be exempted from the testing)
|
Method :
|
a) To
conduct test after window surround grouting has been completely dried and
hardened but before waterproof coating application, normally 3 days after grouting.
|
b) To pour
a continuous and unpressurized flow of water by garden hose evenly along the entire length of the
grouted joints at a rate of 2 m per minute.
|
|
c) To start
the test from the lowest horizontal joint at the sills, then upward along window jambs, and lastly the topmost
horizontal joint at window head.
|
|
d) Detail
testing method and requirements shall be referred to the specification.
|
|
Inspection
:
|
e) To
observe the inner surface of the grout for any water stain or leakage, the test is passed if no water leakage occurs.
|
f) If water
leakage occurs, identify the location for making good, and then repeat from step “b” to “e”.
|
|
g) If there
is still water leakage after the second test, all grouting has to be hacked off
and re-applied for a repeat of the test.
|
|
h) The
waterproof coating can be applied onto the outside surface of the grouting
only after satisfaction of the test result.
|
1. 抆泥試水:
1.1 時間: 在做外牆批盪前
1.2 方法: a) 抆泥後隔3日可安排試水
b) 用氣壓水壺, 約以每分鐘2米的速度, 直接將水沿著抆泥位置外層射水;
c) 試水由窗底開始, 再往兩邊窗側邊, 由上至下, 最後測試窗頂.
1.3 檢查 d) 檢查抆泥的內面有否漏水或水影, 如沒有滲水, 表示抆泥質素沒問題
e) 如有, 紀錄位置, 修補後重複步驟 “b” to “d”.
f) 如果經過第二次測試仍然滲水, 便要將所有抆泥凿去, 重新抆泥後再做測試.
g) 雙方試水滿意後, 才可以讓分判商將防水油塗上外層表面.